---
title: "Asphalt Calculator – Tons, Cubic Yards and Bags | FigureYard"
description: "Estimate how many tons of hot mix asphalt a driveway, parking pad or pothole needs, with cubic yards and bags of cold patch."
url: https://figureyard.com/concrete/asphalt-calculator/
image: https://figureyard.com/og/concrete/asphalt-calculator.png
---

[Concrete & Masonry](https://figureyard.com/concrete/)

# Asphalt Calculator

Enter the length, width and compacted thickness of a driveway, parking pad or pothole to see how many tons of asphalt to order, with cubic yards and cold patch bags.

Reviewed by FigureYard editorial team · Updated October 9, 2026 · 11 sources

*Interactive calculator on the page (inputs: Shape; Length; Width; Diameter; Inside diameter; Thickness; How many identical areas; Extra for waste (%); Price per ton ($)). The results below are for its default inputs.*

**You need**

**7.45** tons

- **3.7** cubic yards
- **100** cubic feet

Or buy bags

- **200** 50 lb cold patch bags

Hot mix asphalt is sold and priced by the ton, so the tons figure is the one to check against a quote. Compacted hot mix weighs about 149 lb per cubic foot, and a short ton is 2,000 lb. The 50 lb cold patch bag used in the bag count yields 0.5 cu ft once it is compacted.

## How to use this calculator

1. Pick the shape. Use a rectangle for a driveway, parking pad or patch, a circle for a round turnaround, and a triangle for a wedge-shaped corner.
2. Enter the length and width in feet and the thickness in inches. Use the compacted thickness, not the loose depth the crew spreads, because the roller packs the mix down.
3. Enter a driveway's bottom and surface courses together as one thickness, or run each course separately and add the two tons figures.
4. Leave the waste at zero for an exact volume, or add a percentage when the base is uneven.
5. Use the tons figure for a per-ton quote and the cubic yards figure for a per-yard quote. For a small hole, use the bag count, since a cubic yard takes 54 bags.
6. Type a price per ton from your quote to see the material cost. Labor, delivery and base work are not included.

## Worked examples

### Single-car driveway

40 ft × 10 ft, 3.5 in thick

- cubic yards: 4.32
- cubic feet: 117
- tons: 8.69
- bags of 50 lb cold patch: 234

### Side-by-side driveway

40 ft × 20 ft, 3.5 in thick

- cubic yards: 8.64
- cubic feet: 233
- tons: 17.38
- bags of 50 lb cold patch: 467

### Round turnaround

30 ft diameter, 3.5 in deep

- cubic yards: 7.64
- cubic feet: 206
- tons: 15.36
- bags of 50 lb cold patch: 413

### Pothole patch

4 ft × 2 ft, 2 in thick

- cubic yards: 0.0494
- cubic feet: 1.33
- tons: 0.0993
- bags of 50 lb cold patch: 3

## Cubic yards of hot mix asphalt for driveway and parking pad sizes, by thickness

| Area | 1.5 in deep | 2 in deep | 3.5 in deep |
| --- | --- | --- | --- |
| 10 × 20 ft | 0.926 | 1.23 | 2.16 |
| 10 × 40 ft | 1.85 | 2.47 | 4.32 |
| 12 × 40 ft | 2.22 | 2.96 | 5.19 |
| 20 × 40 ft | 3.7 | 4.94 | 8.64 |
| 12 × 60 ft | 3.33 | 4.44 | 7.78 |

Cubic yards, exact volume without extra for waste.

## How thick should a driveway be?

A Colorado asphalt association brief on driveways recommends, for an ordinary home driveway, a bottom course of 2 inches and a surface course of 1.5 inches. Local soil and traffic can call for more, so ask the paving contractor before you order. Some owners pour concrete for a parking pad instead, and the [concrete slab calculator](https://figureyard.com/concrete/concrete-slab-calculator/) sizes that job.

Both courses sit on a crushed aggregate base of 6 to 8 inches, which spreads the load from the car over the soil. Order that base separately with the [gravel calculator](https://figureyard.com/concrete/gravel-calculator/), using the same length and width.

## Tons or cubic yards?

Compacted mix weighs about 149 lb per cubic foot, so a cubic yard comes to roughly 4,000 lb, or 2.01 tons. The tons figure in the calculator uses that same weight.

At the surface course thickness of 1.5 inches, a cubic yard covers 216 square feet. State DOT estimating factors use 106 to 115 lb per square yard per inch, so a quote built on that method should land close to the tons figure here.

## Patching a pothole with cold patch

Each 50 lb cold patch bag yields 0.5 cu ft once compacted, so a cubic yard takes 54 bags. Clear out loose debris and square off the edges before you fill the hole.

Build the patch in compacted lifts of 1 to 3 inches, tamping each one before you add the next. A deep hole is filled in several lifts. Buy an extra bag if the hole is uneven, and follow the product label for placement.

## Mistakes to avoid

- Entering the loose depth. Enter the compacted thickness. The roller packs the mix down, so the finished layer is thinner than the loose mix.
- Ordering from area alone. Square footage has no weight until you add the thickness, so measure each course first.
- Mixing up the units. Compare a per-ton quote with the tons figure and a per-yard quote with the cubic yards figure, because the two results are different numbers.
- Skipping the base. Check the base depth with your paving contractor and local building rules before you dig. Asphalt laid straight onto weak soil is more likely to crack and sink.

## Hot mix, warm mix and cold mix: which one do I need?

Hot mix is delivered hot and rolled right away, and it is the standard choice for driveways and parking pads. Warm mix is made at lower temperatures but is paved much like hot mix, so use the tons figure the same way. Cold mix is bagged or bulk material for potholes and small repairs, so use the bag count for it.

## Common questions

### How many tons of asphalt do I need for a driveway?

Convert the thickness to feet, then multiply the length, the width and the thickness to get cubic feet. Multiply the cubic feet by 149 to get pounds, and divide by 2,000 to get short tons.

### How many bags of cold patch fill a pothole?

Work out the hole's volume in cubic feet, then divide by the yield of one bag, 0.5 cu ft, and round up, because you cannot buy part of a bag.

### Can I use cold patch to pave a whole driveway?

Cold patch is meant for holes and cracks. A cubic yard takes 54 bags, and each one is placed by hand, so for a driveway, order hot mix by the ton from a paving company.

### Why does my paving company's weight differ from the calculator?

The calculator uses a single density figure, and real mixes vary by plant, aggregate and how hard they are rolled. Ask the plant how it weighs each load, and compare its delivery tickets with the estimate.

### How many square feet does a ton of asphalt cover?

One ton is 2,000 lb, and hot mix weighs about 112 lb per square yard per inch per square yard for each inch of thickness. Divide the first by the second to get the square yards one ton covers at one inch thick. Multiply by 9 square feet to get square feet, then divide by your compacted thickness in inches.

### How do I use the asphalt calculator with square meters?

Multiply square meters by 10.764 square feet to get square feet, then enter the area and the thickness in inches. To turn the cubic yards result into cubic meters, multiply it by 0.765 cubic meter.

### How much extra asphalt should I order because it compacts?

Crews usually spread the loose mix at about 1.25 times the compacted thickness before the roller packs it down. Enter your finished, compacted thickness, because the tons figure already counts the packed weight. Your paving crew sets the actual loose depth.

## Related calculators

- [Gravel Calculator](https://figureyard.com/concrete/gravel-calculator/)
- [Concrete Slab Calculator](https://figureyard.com/concrete/concrete-slab-calculator/)
- [Cubic Yard Calculator](https://figureyard.com/measure/cubic-yard-calculator/)
- [Sand Calculator](https://figureyard.com/concrete/sand-calculator/)

Reviewed by FigureYard editorial team on 2026-10-09. Formulas are tested against published values, and material figures come from the sources below. [How we build our calculators](https://figureyard.com/editorial-policy/).

## Sources

- [Alaska DOT&PF Estimating Factors (2015): Hot Mix Asphalt](https://dot.alaska.gov/creg/design/highways/Materials/Estimating_Factors_2015.pdf)
- [Illinois DOT plan sheet PL-78579-053: hot-mix asphalt estimating factors](https://apps.dot.illinois.gov/eplan/DESENV/030918/053-78579/PLANS/PL-78579-053.pdf)
- [QUIKRETE Asphalt Cold Patch (No. 1701) product data sheet](https://www.quikrete.com/pdfs/data_sheet-asphaltcoldpatch.pdf)
- [NIST Guide to the SI, Appendix B.8: Factors for units listed alphabetically](https://www.nist.gov/pml/special-publication-811/nist-guide-si-appendix-b-conversion-factors/nist-guide-si-appendix-b8)
- [Colorado Asphalt Pavement Association technical brief: Best Practices for the Use of Asphalt Driveways (2005)](https://www.asphaltinstitute.org/wp-content/uploads/Best-Practices-for-the-Use-of-Asphalt-Driveways-by-the-Colorado-APA-1.pdf)
- [Tennessee DOT Instructional Bulletin 16-16: asphalt mixture quantity factors](https://www.tdot.tn.gov/PublicDocuments/DesignDivision/assistant_engineer_design/design/DGpdf/IB_16_16.pdf)
- [NIST Handbook 44 (2024), Appendix C: General Tables of Units of Measurement](https://www.nist.gov/system/files/documents/2024/01/14/NIST%20HB%2044%202024%20Appendix%20C%20General%20Tables%20of%20Units%20of%20Measurement.pdf)
- [Asphalt Institute (Asphalt magazine): Five handy rules of thumb for successful asphalt pavement construction - Asphalt magazine](https://www.asphaltmagazine.com/5rulespavementconstruction/)
- [NIST Office of Weights and Measures: SI Units - Mass](https://www.nist.gov/pml/owm/si-units-mass)
- [NIST Office of Weights and Measures: Metric (SI) Prefixes](https://www.nist.gov/pml/owm/metric-si-prefixes)
- [NIST Office of Weights and Measures: SI Units - Volume](https://www.nist.gov/pml/owm/si-units-volume)
